INSTALLATION GUIDE

Luxa Sereno 700 — Installation guide

Motorised bioclimatic louvre roof. 8 assembly steps from anchor plate to lamel calibration. ~4 hours, 2-person team.

Total install time

≈ 4 hours total · 2-person team

This guide is the canonical installation reference produced from the same parametric model that drives our CAD. Drawings, dimensions and torque values are nominal and subject to project tolerance.

HOW IT'S BUILT

From foundation to lamels — in under 20 seconds

An accelerated walkthrough of every step from D1 to D8.

ASSEMBLY · 8 STEPS

Step-by-step installation

Build viewD1
D1 — System layout

STEP D1 · 01/08

Place the foot plates

Mark the four corner positions per the site survey, then drill and install M12 chemical anchors. Set each 220 × 220 × 12 mm anchor plate level with shims; verify all four are coplanar within ± 2 mm.

Sub-steps

  1. 1Lay out the four corner positions per the site survey using a chalk line and tape.
  2. 2Verify the W × P rectangle: measure both diagonals — they must agree within 3 mm.
  3. 3Drill four Ø 14 mm holes for M12 chemical anchors at each corner mark.
  4. 4Inject HIT-HY 200 (or equivalent) epoxy into each hole; insert M12 stainless threaded studs.
  5. 5Wait the cure time printed on the cartridge (typ. 30 min @ 20 °C).
  6. 6Bolt the 220 × 220 × 12 mm anchor plate to each stud; level with shims; torque to 60 Nm.
  7. 7Verify the four anchor plates are coplanar within ± 2 mm using a laser level or string line.

Specifications

Anchor typeM12 chemical anchor (e.g. Hilti HIT-HY 200 + HAS-V)
Hole Ø14 mm × 90 mm depth
Cure time30 min @ 20 °C (consult cartridge)
Plate size220 × 220 × 12 mm anodised aluminium
Torque60 Nm
ToleranceDiagonals ± 3 mm · Coplanar ± 2 mm
TIP

Diagonals must match within 3 mm — measure W × P and the two diagonals before drilling. Skipping this check is the #1 cause of misaligned columns later.

WATCH OUT
  • Do not anchor into expansion-joint zones or within 100 mm of slab edges.
  • Substrate must be C25/30 concrete minimum. Lower-grade concrete requires longer anchors and a structural review.

TOOLS

Tape, chalk line, hammer drill (M12), torque wrench, spirit level, shim plates

TIME

45–60 min

MODULE SIZES

Six standard sizes — couplable for any footprint

The Sereno 700 is built around six standard single-module sizes. Each module uses four columns and supports a maximum single-span width of 4.0 m. For larger footprints, modules couple side-by-side or in an L-configuration, sharing intermediate columns.

Size (W × P)AreaModule configurations
3 × 3 m9Single — 4 columns
3 × 4 m12Single — 4 columns
3 × 5 m15Single — 4 columns
4 × 4 m16Single — 4 columns
4 × 5 m20Single — 4 columns
4 × 6 m24Single — 4 columns
Maximum single-span
4.0 m. Larger areas are built by coupling multiple modules.
Module configurations
Single — 4 columns
Louvre rotationUp to 115°
Snow load150 kg/m² (EN 1991)
WindTested per EN 1991 — optional wind sensor
Material6063-T5 aluminium · 98% recyclable